A lot has changed in the city in 15 years, but one constant has been the seemingly never-ending Valley Line saga.
Article content
After many years of setbacks, Valley Line southeast, the 13-kilometre stretch of LRT from Mill Woods to Downtown, is set to open Nov. 4.
Planning on the line started nearly 15 years ago. Stephen Mandel was mayor. Mayor Amarjeet Sohi was still a councillor, and had a stint as a federal cabinet minister ahead of him. The Oilers were just at the start of their Decade of Darkness. The Elks were still called the Eskimos and they were competitive. (They were last in the West in 2008, but made the CFL East Division Final.)
Advertisement 2
Article content
Article content
A lot has changed in the city in 15 years, but one constant has been the seemingly never-ending Valley Line saga.
Here’s a look at how the project unfolded.
January 2008: As former mayor Stephen Mandel calls for his fellow city leaders to press the provincial government for more money to build LRT, city council also endorses a motion from then-councillor Amarjeet Sohi to expedite planning for a line to Mill Woods. City planners began drafting LRT extensions in southeast and west Edmonton.
Early 2009: Planning begins on a Mill Woods to Downtown route.
December 2009: City council approves LRT expansion to NAIT, west Edmonton and the southeast, setting the stage to seek funding for the projects. At the time, the southeast leg was estimated to cost $900 million to $1.2 billion. During public consultations, a transit official told the public that if funding came through, trains could be running to Mill Woods by 2014.
January 2011: City council officially greenlights the southeast LRT alignment, solidifying the track’s route and station locations.
Related Stories
-
Valley Line back on track after repairs to cracked piers
-
Edmonton’s Valley Line LRT needs to replace around 140 km of signal cable, no opening date set
-
Valley Line Southeast LRT set to open ‘this fall’ after completed cable replacement
Article content
Advertisement 3
Article content
May 2012: After spending much of 2011 wrestling with the question of how to pay for more LRT, city council makes the call for the southeast line to be a public-private partnership (P3), with plans to apply to the federal P3 fund. Coun. Don Iveson said at the time, “Frankly, doing this seems to be the only way we can get federal funding.”
March 2013: The federal government announces $250 million in funding from the P3 Canada Fund.
March 2013: The name Valley Line is announced.
August 2013: The Valley Line southeast is pushed back from its initial 2019 opening target as city council decides against borrowing $515 million to get it started, and waits for the provincial and federal governments to solidify their funding commitments instead. At this point, the total price tag has been updated to $1.8 billion.
November 2013: The preliminary design of the 27-km line from Mill Woods to Lewis Farms is completed.

March 2014: Premier Alison Redford announces a $600-million assistance package for the Valley Line southeast, filling the final missing piece for the city to hire a construction consortium.
Advertisement 4
Article content
August 2014: The city announces a three-name shortlist of bidders for the P3 project.
February 2016: The City of Edmonton signs a contract with TransEd partners — a group led by Bechtel, Bombardier, EllisDon and Fengate Capital Management — to build the Valley Line southeast and maintain it for 30 years.

April 2016: Politicians mark a groundbreaking ceremony for Valley Line construction, with plans to build from Mill Woods Town Centre to Downtown and open the LRT expansion in 2020.
March 2018: A construction complication emerges as crews discover a “car-sized” concrete slab buried nine metres under a platform where crews are building a bridge across the North Saskatchewan River. The issue holds up work for more than two months, putting the bridge completion behind schedule.
December 2019: After the quarterly report on the project says progress is roughly 30 per cent behind where it should be, TransEd says the project won’t be finished until “at least” 2021, partly owing to the concrete slab delays.
October 2021: TransEd says the goal to welcome riders by the end of the year won’t be met, with COVID-19 affecting both their workforce and the supply chain. A new opening date is set for early 2022.
Advertisement 5
Article content
December 2021: The Valley Line completion deadline is revised again, to summer 2022, with pandemic impacts again cited as the reason.

August 2022: With work on the southeast transit expansion all but completed, TransEd announces a fourth delay due to cracks discovered in many of the piers that support the elevated LRT track. More construction will be needed to strengthen as many as 18 concrete piers, and it’s still unclear just how much longer Edmontonians could wait for the southeast line that’s almost two years behind schedule.
December 2022: TransEd announces the completion of repairs to cracked piers and state the hope is to open the line “as soon as possible.”
April 2023: Concerns were raised about the safety of the line after a man sleeping near the tracks was hit by a train. This followed a number of collisions involving vehicles turning right against traffic signals.
June 2023: TransEd announces yet another delay for the Valley Line, stating that 140 km of signalling line needed to be replaced after some were found to be oxidized. The replacement would “improve the long-term system reliability” on the line.
September 2023: TransEd announces the cable replacement along the line has been completed and that the line can resume testing in preparation for a fall opening.
October 2023: The city announces a Nov. 4 opening date for the line.
Article content
Comments
Postmedia is committed to maintaining a lively but civil forum for discussion and encourage all readers to share their views on our articles. Comments may take up to an hour for moderation before appearing on the site. We ask you to keep your comments relevant and respectful. We have enabled email notifications—you will now receive an email if you receive a reply to your comment, there is an update to a comment thread you follow or if a user you follow comments. Visit our Community Guidelines for more information and details on how to adjust your email settings.